The first 30 to 60 days of a construction project establish patterns that persist for the entire construction period. The communication cadence that develops in the early weeks, the document control discipline that is or isn’t established at the start, the GC’s approach to schedule management, and the owner’s representative’s posture toward the project all become embedded behaviors that are difficult to change once they are set. Projects that start well, with clear communication protocols, an established baseline schedule, a complete submittal log, and an owner’s rep who is actively engaged from the first day, almost always perform better than projects where the first weeks are disorganized.
The Preconstruction Kickoff Meeting
The preconstruction kickoff meeting, typically held before ground is broken, once contracts are executed, is the first opportunity to establish the project’s management culture. Who attends matters: the owner, the owner’s representative, the architect, the key design subconsultants, the GC’s project manager and superintendent, and the key subcontractors (if they are already engaged) should all be present. A kickoff meeting that is attended only by the GC’s principal and the owner is a meeting that doesn’t reach the people who will execute the project every day.
The kickoff meeting should accomplish specific outcomes, not just introduce participants. These outcomes include: confirmation of the project schedule baseline and the milestone dates that both parties have committed to; establishment of the project’s communication protocols (who reports to whom, what format, at what frequency); review of the submittal schedule and confirmation that it is tied to the construction schedule; review of the contract documents for any clarifications needed before mobilization; and establishment of the change order process, including who has authority to authorize changes and what documentation is required before change work proceeds.
A kickoff meeting that produces meeting minutes, distributed to all attendees within 48 hours, converts the discussions into documented commitments. Projects without kickoff meeting minutes often experience disputes later about what was agreed at the start of the project.
The Baseline Schedule: The Project’s Single Source of Truth
Within the first two weeks of project start, the GC should submit a detailed baseline construction schedule for owner’s representative review. The baseline schedule, prepared in CPM (critical path method) format, should show every major work activity, its duration, its logical dependencies on other activities, and its relationship to the project milestones.
The owner’s representative’s review of the baseline schedule is substantive, not perfunctory. A schedule with logical dependencies that don’t reflect actual construction sequence, with activity durations that are optimistic relative to the project’s scope, or with insufficient float on the critical path provides false confidence about the project’s achievability. The owner’s rep should review the schedule against their knowledge of the project type and market, identify activities where the duration assumptions seem optimistic, and discuss those concerns with the GC before the baseline is accepted.
Once the baseline schedule is accepted, it becomes the reference point for all subsequent progress reporting. Every progress update, at every project meeting, at every draw cycle, should be measured against the baseline schedule. The question “are we on schedule?” means “are we on the baseline schedule?”, not “are we doing as well as we expected based on current conditions?”
Submittals and Long-Lead Items
The first weeks of a project are when the submittal process must be activated. The GC should submit the project’s submittal log, a comprehensive list of all required submittals, organized by specification section and tied to the construction schedule, within the first week of project start. This log becomes the owner’s representative’s tracking tool for the entire submittal process.
Long-lead items require immediate attention. Equipment and materials with fabrication and delivery lead times that extend beyond 12 to 16 weeks, elevators, specialty HVAC equipment, curtain wall systems, precast concrete components, must be ordered early or their delivery will delay the construction schedule. The owner’s representative should identify long-lead items at project kickoff, confirm that the GC has a procurement plan for each, and monitor that plan against the construction schedule throughout the early weeks of the project.
A project that reaches the point in the schedule where elevator installation is supposed to begin and discovers that the elevator was never ordered is a project with a 6-month schedule problem that started with a 3-week oversight at project kickoff.
Communication Protocols and Meeting Cadence
The communication protocols established at project kickoff, who receives what information, on what schedule, in what format, should be documented and distributed to all project participants. Standard protocols for multifamily and commercial projects:
Weekly OAC meetings. Owner-Architect-Contractor (OAC) meetings are the primary project coordination forum, typically 60 to 90 minutes, covering schedule status, RFI and submittal status, change order status, and open items. The owner’s representative typically chairs these meetings and prepares or reviews the minutes.
Monthly draw review. The draw cycle, including inspection scheduling and draw package review, should be calendared at project start so all parties know the schedule for each monthly draw.
Design team coordination meetings. For projects with active design questions during construction, because the documents weren’t complete at construction start, or because field conditions have generated design decisions, the frequency and format of design team coordination meetings should be established at kickoff, not improvised when questions arise.
Projects that invest in a thorough, well-attended kickoff meeting, with documented outcomes and clear accountability for each commitment made, start with the organizational alignment that sustains project performance through the inevitable challenges that arise during any significant construction program.
The kickoff meeting’s value compounds throughout the project. The communication protocols established at kickoff shape how problems are surfaced and resolved for the next 18 months. The baseline schedule accepted at kickoff is the reference point for every schedule discussion that follows. The documentation discipline, or lack of it, established in the project’s first two weeks tends to persist. Starting well is not a guarantee of finishing well, but starting poorly makes finishing well much harder.
Related: Owner’s Representative Services · Construction Management Services · Preconstruction Planning · Construction Management Guide
Markets: Construction Management Seattle WA · Construction Management Austin TX · Owner’s Representative El Paso TX